Step 1: Groundbreaking ceremony --- Technical Staff Standby — Staking out — Leveling & Trenching
-
—Rebar Installation —
Vapor Barrier Installation — First Inspection Check-off
-
Step 2: Material Check — Underground Plumbing Installation (Supply Water Line, Sewer Line, Gas Line) — Second Inspection Check-off
-
Step 3: Pouring Concrete - Third Inspection Check-off
(First Phase Completion)
-
Step 4: Wood Framing (Floor, Wall, & Roof) --- Penetration Over Wood Framing (Water & Electric Line) — Forth Inspection Check-off (Rough Framing & Rough Plumbing) — Enclosing Exterior Wall/Roof (Wood Sheathing) — Enclosing Exterior Wall (Waterproof & Stucco) — Electric Panel Installation — HVAC Installation -- Insulation Installation — Fifth Inspection Check-off --- Enclosing Interior Walls & Ceilings (Gypsum Board) --- Roofing (Waterproof P叩er & Roofing Material) --- Sixth Inspection Check-off
-
Step 5: Exterior Doors & Windows Installation --- Seventh Inspection Check-off - Interior Construction - Apply compound & Taping, Shower bathroom Waterproofing --- 24-48 Hours Waterproofing Test
-
Step 6: Install Water Heater, Lighting Fixtures (Fixed), Cabinets, Plumbing Fixtures, Flooring Material, Staircase Hand & Guardrail ---Seventh Inspection Check-Off
-
Step 7: Install Kitchen Appliances, Lighting Fixtures (Flexible), Media & Audio System, Air Conditioning System, along with Company Supervision Engineer to check-off quality of the whole house with the Owner - Eighth Inspection Check-Off
-
Step 8: Construction Finalization (Signature on Construction Acceptance Form, Owner receiving Home Warranty, Key, Manual, and Remote Controls) - Completion of Construction